PROJECT
|
FINANCIER
|
OBJECTIVE
|
STATUS
|
|
|
Ayago Interconnection project (10km)
|
China Exim Bank
|
Bujagali Interconnection Project To provide adequate transmission capacity to evacuate power generated at Ayago Hydro Power Station (HPS).
|
Feasibility concluded
|
|
Lira-Gulu-Agago 132 kV T/L (140km)
|
Government of Uganda
|
To provide adequate transmission capacity to evacuate power generated at Agago/Acwa 88MW HPS
|
RAP implementation commenced Feasibility completed
|
|
Mirama-Kikagati-Nsongezi 132 Kv T/L (38km)
|
Norwegian Gov’t
|
To provide adequate transmission capacity to evacuate power generated from Kikagati and Nsongezi power plant.
|
Feasibility completed
|
|
Mbale-Bulambuli 132 kV T/L (60km)
|
Government of Uganda
|
To provide adequate transmission capacity to evacuate power generated from renewable projects like Siti I & ii, Muyembe, Ngenge i & ii
|
Feasibility is ongoing
|
|
Nkenda-Mpondwe-Beni (DRC) 220kV T/L (72.5km)
|
Norwegian Gov’t
|
Regional grid interconnection for power trade and improvement of security of power supply
|
Feasibility & RAP studies completed
|
|
Masaka-Mutukula-Mwanza 220 kV T/L (82km)
|
Sourcing for financing through EAC
|
Regional grid interconnection for power trade and improvement of security of power supply
|
Feasibility & RAP studies completed
|
|
Masaka-Mbarara 220 Kv T/L (135km)
|
Sourcing for financing
|
To provide adequate transmission infrastructure to meet the energy needs for in the project area.
|
Feasibility completed
|
|
Hoima-Kinyara-Kafu 220kV T/L (92km)
|
International Development Association (IDA)
|
Provision of adequate transmission capacity to meet power supply needs of western Uganda and evacuate power from project areas.
|
Feasibility completed Completion in 2018
|
|
Kawanda-Masaka 220 kV T/L (137km)
|
WB-IDA under Electricity Sector Dev’t Program (ESDP)
|
Reinforcing the capacity of the western transmission line to cater for increased demand in Masaka, Mbarara, Kasese, Fort-portal, Kabale, Bushenyi and the environs
|
Completion in 2018
|
|
Opuyo-Moroto 132kV T/L (160km)
|
Sourcing for financing
|
Provision of adequate transmission capacity to cater for the projected demand in the Karamoja sub region
|
RAP implementation at 75% EPC procurement ongoing Completion in 2019
|
|
Upgrade of Mutundwe (60MVA), Kawanda (40MVA),Lugogo (60MVA),Kawaala, 132/33/11kV substations
|
Government of Uganda
Islamic Dev’t Bank
|
Provision of adequate transmission capacity to absorb power generated from Bujagali HPP and improvement of power supply reliability and quality in Nanugongo, Kasubi, Kawaala and Wakiso district.
|
|